Why Is the Roof Beam Deeper Near the Column?

Look at a cross-section of a steel warehouse. Follow the underside of the sloping roof beam toward the sidewall. On some portal-frame drawings, its lower edge slopes down more sharply near the column, forming a wedge. This locally deepened section is called an eaves haunch. It helps the frame resist bending at the connection, and it affects the space beneath it.


Portal-frame cross-section showing an eaves haunch and the vertical clearance above goods on a sidewall rack.

AI-generated concept illustration of an eaves haunch and clearance above a loaded rack. Not to scale or a construction drawing.

C = minimum vertical clearance above the stored load at the illustrated rack position.

View full-size diagram

Why Add Depth at the Corner?

In a typical portal frame, the column and the sloping roof beam, or rafter, work together. Their connection resists rotation. As the frame carries load, the bending demand can be high near that joint.

An I-shaped rafter has a flange at the top and another at the bottom. Considering bending alone, one flange is in tension and the other is in compression. Increasing the distance between them gives those forces more leverage to resist bending. A haunch provides extra depth near the joint while allowing a shallower rafter farther along the roof.

What Does This Mean for a Row of Pallet Racks?

Suppose a proposal lists an 8 m eave height and you plan to install racks along the sidewall. That figure alone cannot tell you whether the top pallet will fit. First, check which points the 8 m dimension connects on the supplier’s drawing. Then look at the underside of the steel above the proposed rack. A dimension taken near the middle of the building can miss the low point at the haunch.

For broader planning considerations, see our steel warehouse buildings guide.

What Should You Ask the Supplier to Show?

Ask for a frame cross-section showing the finished floor, the sidewall column and the nearest rack together. Mark the rack’s position relative to the column and the highest point of the goods on the top pallet. Ask the supplier to dimension the smallest vertical gap between the stored load and the steel above it, checking the full footprint of the rack and its loaded pallets.

Then check whether sprinklers, lighting or ducts occupy any of that space, and confirm the operating and fire clearances with the relevant designers.

A useful drawing request is: “Please show the minimum vertical clearance above our fully loaded sidewall rack at its actual position.” That gives the supplier a dimension they can mark and your warehouse team a dimension they can use.

For another sidewall layout issue, read about a warehouse door that conflicts with X-bracing.